Most mornings this year, the slow part of the drive from Bayfield to Durango has been on the Durango end. CDOT's 2026 resurfacing runs about six miles of US 160, from Elmore's Corner at the CO 172 intersection to the Durango High Bridge just north of Walmart, mile points 86 to 92. In the week of September 28, crews were still milling and paving between Three Springs and Highway 3. They were working toward Walmart, with lane shifts and closures in place around the clock and daytime delays in both directions.
The project is scheduled to finish in November. After that, the next round of major work on this corridor is on the Bayfield side of Elmore's Corner. One project is a seven-mile CDOT rebuild that starts where this year's paving ends. The other is the Town of Bayfield's new intersection at the east edge of town. Both are expected to be active in 2027. The winter in between is the only stretch on the current calendar with no large project on the commute.
The drive, west to east, by project
| Stretch of US 160 | Project | Lead | Current timeline |
|---|---|---|---|
| Durango High Bridge to Elmore's Corner, MP 86 to 92 | Resurfacing, guardrail, ADA crossings | CDOT with Elam Construction | Began March 23, 2026; completion anticipated November 2026 |
| Elmore's Corner to Dry Creek near CR 223, MP 91.4 to 98 | Four-lane rebuild, CR 225 intersection, wildlife underpasses | CDOT design-build | Construction begins spring/summer 2027, three seasons through 2030 |
| US 160 at East Bayfield Parkway and East Oak Drive | New intersection, about $4.2 million | Town of Bayfield, CDOT review | Expected under construction most of 2027 |
The mile points show how the projects connect. This year's resurfacing reaches its east end at Elmore's Corner, around MP 92. CDOT starts the Elmore's East project at MP 91.4. Together they form one continuous construction corridor, built in two phases, with this winter between them.
What's left on the 2026 paving job
CDOT started the resurfacing on the east end, with curb reconstruction at Elmore's Corner, and has been moving west toward Durango. The last piece of the plan is deck repair and resurfacing on the High Bridge. CDOT hasn't announced a date for the bridge work. The September 28 traffic update lists it as part of the project but gives no timing. If you're planning around the November finish, the High Bridge is the last open item, and the date could shift.
The Grandview Interchange ramps have also had staggered overnight closures, set to run through early October. The ramps are part of the original scope, which includes settlement repairs and resurfacing on the Grandview exit ramps. The scope also covers drainage and inlet repairs in the concrete median from south of Home Depot to old Farmington Hill.
Work hours, per CDOT:
- Sunday night through Friday morning, 7 p.m. to 7 a.m.
- Single-lane closures, lane shifts and shoulder closures
- Delays of up to 15 minutes
- 45 mph limit in the work zone
- Lane closures and traffic shifts stay in place 24/7, so daytime slowdowns happen even though most work is done at night
Once the cones are gone, you'll have a few new things to show for it. The guardrail is 31 inches high, built to newer safety standards. ADA-compliant pedestrian ramps and crosswalks are going in at Dominguez Drive, River Road, Three Springs Boulevard and CO 172/CR 234 at Elmore's Corner. The project hotline is 970-456-1481 if you need a closure answer before you leave the house.
Elmore's East turns the middle of the commute into a work zone
The bigger project starts at the end of the new pavement. CDOT's Elmore's East project covers seven miles of US 160, from Elmore's Corner at MP 91.4 to Dry Creek near La Plata County Road 223 at MP 98. The estimated cost is about $100 million. The plan includes:
- A four-lane highway with dedicated left-turn lanes
- A rebuilt intersection at CR 225 and US 160, around MP 94
- Two wildlife underpasses, a bridge replacement and wildlife fencing on both sides of the highway
- As many alternating passing lanes as possible between CR 225 and Dry Creek, MP 94 to 98
The procurement documents add detail. Between CO 172 and CR 225, the design calls for four 12-foot through lanes plus a two-way center left-turn lane. Between CR 225 and CR 223, it calls for at least one mile of passing lane in each direction.
The CR 225 intersection is the piece most likely to change how a daily commute feels, and it isn't final yet. A 2021 intersection study presented to the La Plata County Board of Commissioners named a roundabout as the preferred option. CDOT says other designs will still be evaluated based on safety, environmental impacts and cost. If a roundabout is built, it would have a truck apron in the center so heavy trucks and livestock haulers can get through. CDOT's FAQ also says drivers turning onto US 160 from the county road have a hard time entering the highway safely, especially at peak commute times.
The timing is the main point for Bayfield drivers. CDOT plans construction over three seasons, 2027 through 2030. The procurement documents require two lanes of traffic to stay open throughout construction. CDOT hasn't published a traffic-control plan beyond that requirement. It also says the current plans are conceptual renderings that can't be shared publicly yet and may change once a contractor is hired.
That contractor hasn't been chosen. In March 2026, CDOT shortlisted three design-build teams: AMES/WILSON, AUI/AECOM and RL Wadsworth/RS&H. CDOT revised parts of the final request for proposal on September 11, 2026, and proposals are due October 22. The posted schedule also lists a "Summer/Fall 2026" notice of award, which doesn't fit neatly with an October 22 proposal deadline. After that come a notice to proceed in winter 2026-27, a public meeting in spring 2027, and the start of construction in spring or summer 2027. The spring 2027 public meeting will likely be the first look at how the selected team plans to manage traffic.
On funding, CDOT received a $59 million federal INFRA grant in 2024. It lists another $52 million in state and federal money from SB21-260, FASTER and Bridge Enterprise. Those two figures add up to $111 million, more than the roughly $100 million total on the project's overview page. CDOT doesn't explain the difference, so the exact budget is still an open question.
Bayfield's own intersection lands in the same year
The east end of the commute has its own project. The Town of Bayfield's East Intersection Project covers the US 160 and East Bayfield Parkway intersection and the East Oak Drive alignment, with engineering plans by SEH. Town trustees approved $148,980 for 60% engineering design in June 2022. The town held public open houses on March 1 and March 14, 2023. The town's project page links the 60% engineering plan and describes it as a signalized intersection. The linked signing and striping sheet has a print date of February 28, 2023. The design has since moved into a final phase, so the 2023 drawing may no longer show exactly what will be built.
In a September 5 Durango Herald story by Jane Rooney, Town Manager John Waters said the project has been in the works for two decades. It is now in final design for CDOT review, with an estimated cost of about $4.2 million and some funding earmarked by the federal congressional delegation. He said it will probably be under construction for most of next year, meaning 2027.
"The intersection is the first step in getting that safe access across the highway," Waters said. He added that it will "open up some commercial property and additional housing property on the east side of Bayfield."
The same article explains why the intersection is moving ahead while other town projects wait. Waters said the town budget has been tight this year. Projects tied to basic needs and safety come before improvements to Mill Street, where the center section of sidewalk is still waiting for funding after the east and west ends were rebuilt.
How the 2027 calendar stacks up
If both schedules hold, 2027 will have construction at two points on the Bayfield half of the drive. The town's intersection will be at the east edge of Bayfield. CDOT's four-lane work will run from Elmore's Corner to Dry Creek. Neither agency has published a start month, so it's too early to say how much the two will overlap. The Elmore's East work will then continue into 2028 through 2030, well after the town's intersection is expected to be done.
Here are the key dates for the months ahead:
- Early October 2026: Overnight closures of the Grandview ramps wrap up
- October 22, 2026: Elmore's East proposals due from the three shortlisted teams
- November 2026: Resurfacing completion anticipated, with the High Bridge deck work the last unscheduled piece
- Winter 2026-27: Elmore's East notice to proceed
- Spring 2027: CDOT public meeting on Elmore's East
- Spring/summer 2027: Elmore's East construction begins; the town's intersection is expected to be under construction for most of the year
For Bayfield drivers, the slow spots will shift from Three Springs and Grandview to Elmore's Corner, CR 225 and the east edge of town.
If you're weighing whether to sell before or after the construction years on the Bayfield end of US 160, or wondering how a new intersection at East Bayfield Parkway could affect your home's value, Judi Mora can walk you through the timing with local context. Request a Free Home Valuation, and Judi will factor in where your home sits along the corridor.